Transform your bathroom in just 15 to 20 working days!

You’ll be amazed at how quickly your custom designed bathroom can be put together by our team of expert tradespeople. Once you approve our quote detailing the scope of work we are to deliver, we will agree on a date to begin your renovation.

A typical bathroom renovation takes between 15 to 20 working days to complete from project start.

 

Here’s how a standard project progresses:

  • Days 1 and 2 – Remove existing bathroom

    We will spend the first day or two stripping your existing bathroom and removing current fixtures. With protective floor coverings from the work site to the front door, you can relax knowing your house is being looked after. We remove rubbish as we go and clean up at the end of each day.

  • Days 3 to 7 – Plumbing, electrical work and construction

    A licensed plumber will review your plumbing and drainage and make any changes your new bathroom requires. A licensed electrician will complete any new wiring for features such as lights, floor heating, power points, exhaust fans and heat lamps. We always use quality products that meet Australian Standards and will advise you on any safety switches the law may require. Our carpenters and plasterers will complete any structural aspects you need, including walls, doors, architraves, windows, ceilings and cornices, as well as carrying out minor repairs. Our renderer can plumb your walls if required. (Please note: we will require approximately two extra days if render is needed, in order for it to dry).

  • Days 8 to 11 – Waterproofing

    A waterproof membrane will be applied to the entire bathroom floors and shower walls, with upturns at floor and wall junctions as per Australian Standards.

  • Days 12 to 15 – Tiling

    Whether your tiles are ceramic, mosaic, vitrified marble, stone or porcelain, our tilers will professionally lay your wall and floor tiles using fine, sanitised grout and adhesives. All our tiling have mitred edges, we do not use tile trims.

  • Days 16 to 17 – Install fittings

    Our plumber and carpenter will fit out your bathroom and measure for your shower screen if required.

  • Day 18 – Clean, polish and final inspection

    We clean, polish and conduct a final inspection of your new bathroom.